The demolition work of the street lamp line on both sides of Jianjun Road begins, and travels at night.
High Carbon Spring Steel Wire,High Carbon Steel Wire,Soft Annealed Iron Wire,Low Carbon Steel Wire Iron Wire anping yaqi wire mesh co.,ltd , https://www.yaqisteelwire.com
With the further advancement of the construction of the underground civil air defense commercial street of Jianjun Road, the demolition work of the street light pipelines on both sides of Jianjun Road began gradually. It is reported that the street lamp management department of the main city construction bureau is responsible for the demolition of the street lamp. The staff of the department reminded that after the street lamp line was dismantled, there was no light at night in some areas, so people should be careful when travelling.
This project requires the removal of more than 100 side lights, more than 100 street lights, a total of more than 200 lights, and dozens of kilometers of underground cables. Xu Kechang, the maintenance center of the City Street Light Management Office, said that starting from last week, we first removed the sidelights of all sections involved in the construction and removed the lampshades of the two bypass lights. According to reports, the main purpose of removing the lampshade is two. First, the construction vehicles are guaranteed to enter the site smoothly, because many large construction machinery are very high in height and it is easy to hit the lampshade. The second is to ensure that the lampshade does not fall into the crowd due to construction effects, thus ensuring the safety of pedestrians and construction workers.
In addition, the Street Light Management Office has also removed some of the light poles that are about to enter or have already entered the construction section. By August 10th, the street lamp line of the construction section will be completed to ensure that other departments can smoothly enter the construction.
Then why not remove it all at once? Xu Kechang told reporters that many light poles and a large number of underground cables have been buried for a long time and need to be excavated by large working machines. When the large-scale work machine enters the market, it is necessary to wait for the road section to be closed, and the big guys such as transformers, pillars and trees at the roadside can move away. If you don't wait for the previous work of other parts to be completed, the street lamp management office will rush into the construction, which is difficult to enter, and it is easy to damage the urban public facilities. Even if the construction is not in place, the cable can be cut off. Therefore, the entire street lamp pipeline project needs to cooperate with other relevant departments to promote and complement each other.
Mr. Xu also reminded the public that due to the removal of the side lights of some sections of Jianjun Road and the streetlights on some roads, some places are darker at night, and citizens who travel at night must pay attention to safety. With the deepening of the project, these sections will be gradually closed and the vehicles will be unable to pass. The citizens should pay attention to relevant information in a timely manner and reasonably adjust the travel routes.